This project comprised the fitout of a 7,000 sf data hall at 1000KW critical load. It included the installation and commissioning of the following:
• RDUs
• Cabling for power supply from the PDUs to RDUs and from RDUs to server racks.
• Novec 1230 Fire suppression system with BMS
• Security system
• Ductwork for telecoms and fibre
• Installation of server racks with iPDU system
• Overhead cable basket & fibre trunking system
Client :
Singtel
Sector :
Mission Critical
Location:
Hong Kong
Size:
7,000 sf
Role:
Design & Build Contractor